Sometimes, a PO number does not end with -001 or continue in sequence. This happens even when the PO is created within a project.
Solution
Purchase order number not ending with -001 and so on, even though it was created within a project
If a PO is only linked to the project and not a specific Job, it won't follow the -001 sequence. Here is how to associate the PO with a job.
In the main navigation bar, click Purchasing or Inventory.
In the left side menu, click on Purchase Orders
Locate the PO in the applicable tab: Pending, Sent, Partially Received, Received, Canceled
Click on the hyperlink in the PO. No. column to view the PO details
Click on the Actions dropdown and then select Edit
In the Job # field, select the appropriate job
Click Save