# Balance to finish and 100 percent completed discrepancy

## Problem

On a project, the balance to finish shows a value, although the project page says it is 100% completed.

## Solution

1. Go to the Application for Payment table.
2. Hover your mouse on the **More** icon next to 100%. The percentage shows a different value. The discrepancy is due to rounding to the nearest decimal.
3. Adjust billing accordingly.

This resolves the discrepancy between the balance to finish and 100% completed on the Application for Payment table.