--- title: "Use change orders to reflect cost adjustments" slug: "use-change-orders-to-reflect-cost-adjustments" updated: 2026-10-26T17:15:27Z published: 2026-10-26T17:15:27Z canonical: "help.servicetitan.com/use-change-orders-to-reflect-cost-adjustments" --- > ## Documentation Index > Fetch the complete documentation index at: https://help.servicetitan.com/llms.txt > Use this file to discover all available pages before exploring further. # Use change orders to reflect cost adjustments ## Overview When a project is in progress, there may be times when changes or modifications to the contract budget need to be represented in ServiceTitan. Cost adjustments are a form of change orders that can adjust the cost budgets for a project. --- ### #### Who uses this feature - Administrators, office employees, managers, accountants, bookkeepers, and project managers - Applies to Residential and Commercial Construction business types and project management customers - Applies to all trades ## Things to know - Cost adjustments are change orders that focus on costs instead of revenue. - Projects can have multiple change orders. - An original Sold estimate is required to make a change order. - The project type of the project must have estimates enabled to create an estimate. For more, see [Create and use project types](/construction/docs/create-and-use-project-types). - When you add a change order to an Application for Payment (AFP), the AFP automatically groups the underlying estimate lines into summary groups on the Schedule of Values (SOV). Each summary group represents a distinct category of work, such as a specific trade, cost type, or user-defined SOV description. ## Create a cost adjustment Change orders are used to make modifications to your project and contract, and typically reflect changes in the contract value or revenue. Cost adjustments instead focus on cost related to the budget of a project. For example, you can use cost adjustments if you have a decrease in the total scope of a project or need to add costs to a specific phase for more accurate budgeting. To create a cost adjustment, complete the following steps to create the change order: 1. Search for and open the project you want to set up a change order for. 2. Click the **Actions** dropdown and select **Build Estimate**. ![Dropdown menu showing various action options including 'Build Estimate' highlighted.](https://cdn.document360.io/961862ab-d0f2-4d91-bb62-a62ee8184eff/Images/Documentation/use-change-orders-to-reflect-cost-adjustments-image-9va1rny1.png?sv=2026-02-06&spr=https&st=2026-10-31T00%3A42%3A58Z&se=2026-10-31T01%3A42%3A58Z&sr=c&sp=r&sig=oVx3KM2d2o%2Foqzg5SQI7sGH%2FnOQA5r%2FvX4OFRfvPp38%3D) 3. On the *Build Estimate* window that opens, click the **Create New Opportunity** tab. ![User interface for creating a new opportunity in an estimate builder tool.](https://cdn.document360.io/961862ab-d0f2-4d91-bb62-a62ee8184eff/Images/Documentation/use-change-orders-to-reflect-cost-adjustments-image-pdv448xq.png?sv=2026-02-06&spr=https&st=2026-10-31T00%3A42%3A58Z&se=2026-10-31T01%3A42%3A58Z&sr=c&sp=r&sig=oVx3KM2d2o%2Foqzg5SQI7sGH%2FnOQA5r%2FvX4OFRfvPp38%3D) 4. Click the **Business Unit** dropdown and select the business unit (BU) for which you want to create an estimate. 5. When finished, click **+ Build Estimate**. ![Interface for creating a new estimate in construction with template selection options.](https://cdn.document360.io/961862ab-d0f2-4d91-bb62-a62ee8184eff/Images/Documentation/use-change-orders-to-reflect-cost-adjustments-image-hv5dlikn.png?sv=2026-02-06&spr=https&st=2026-10-31T00%3A42%3A58Z&se=2026-10-31T01%3A42%3A58Z&sr=c&sp=r&sig=oVx3KM2d2o%2Foqzg5SQI7sGH%2FnOQA5r%2FvX4OFRfvPp38%3D) 6. On the *Create Estimate* screen that opens, [build the new estimate](/construction/docs/add-an-estimate-to-an-opportunity). 7. If you're adding the change order to an Application for Payment, follow these best practices: 1. Add a project label to all items in the change order. Project labels determine how the change order estimate lines are organized into summary groups on the Schedule of Values (SOV). For more, see [Use project labels](/construction/docs/use-project-labels). 2. When you initiate an Application for Payment, the AFP automatically groups the change order's estimate lines into itemized summary groups on the Schedule of Values (SOV). Each summary group represents a distinct category of work based on trade, cost type, or user-defined SOV description. 1. This is different from the initial estimate, where scheduled values are organized based on the project labels assigned. 2. When an invoice is generated for the change order, service items are added using the same logic as the initial estimate. 3. Actual billing is reported on the *Budget vs Actual (BvA)* table based on project labels assigned using the same logic as service items from the initial estimate. 3. When the Change Order Estimate status is updated to *Sold*, enable the **Change Order** option on the *Estimate* screen. This ensures that the change order is accounted for in the *Application for Payment* summary. You can find change order details in the *Net change by Change Orders* and *Change Order Summary* sections. ![Billing information for Greta Smith with options to change order and view opportunity.](https://cdn.document360.io/961862ab-d0f2-4d91-bb62-a62ee8184eff/Images/Documentation/use-change-orders-to-reflect-cost-adjustments-image-nxd9sjyf.png?sv=2026-02-06&spr=https&st=2026-10-31T00%3A42%3A58Z&se=2026-10-31T01%3A42%3A58Z&sr=c&sp=r&sig=oVx3KM2d2o%2Foqzg5SQI7sGH%2FnOQA5r%2FvX4OFRfvPp38%3D) 4. To view the itemized breakdown of a change order, open the Continuation Sheet and click on the change order in the Schedule of Values column. The summary groups for that change order display with their individual values. ### Example You underestimated the material budget for the rough-in phase of a project, and midway through the phase, you realize that you need to reflect the added cost for materials through a cost adjustment. By building a change order, you can add a non-chargeable material to capture the additional costs you want to add to your budget. The material, based on this example, is labeled **Rough-In > Materials**. ![Table displaying material costs, project labels, and cost adjustment details for a job.](https://cdn.document360.io/961862ab-d0f2-4d91-bb62-a62ee8184eff/Images/Documentation/use-change-orders-to-reflect-cost-adjustments-image-9uh0uc6f.png?sv=2026-02-06&spr=https&st=2026-10-31T00%3A42%3A58Z&se=2026-10-31T01%3A42%3A58Z&sr=c&sp=r&sig=oVx3KM2d2o%2Foqzg5SQI7sGH%2FnOQA5r%2FvX4OFRfvPp38%3D) This adds $2,000 in budgeted costs to the **Rough-In > Material** category on the *Budget vs Actual* table. Prior to the cost adjustment, the budgeted total was $200 in costs. ![Budget vs Actual table highlighting materials expense of $2,200.00 in project costs.](https://cdn.document360.io/961862ab-d0f2-4d91-bb62-a62ee8184eff/Images/Documentation/use-change-orders-to-reflect-cost-adjustments-image-pst7bhnm.png?sv=2026-02-06&spr=https&st=2026-10-31T00%3A42%3A58Z&se=2026-10-31T01%3A42%3A58Z&sr=c&sp=r&sig=oVx3KM2d2o%2Foqzg5SQI7sGH%2FnOQA5r%2FvX4OFRfvPp38%3D) The final result reflects the cost adjustment for rough-in materials on the *BvA* table. You can drill into the materials to see that reflected by line item. ![Budget details showing expenses and itemized costs for materials and work.](https://cdn.document360.io/961862ab-d0f2-4d91-bb62-a62ee8184eff/Images/Documentation/use-change-orders-to-reflect-cost-adjustments-image-ei3itcvt.png?sv=2026-02-06&spr=https&st=2026-10-31T00%3A42%3A58Z&se=2026-10-31T01%3A42%3A58Z&sr=c&sp=r&sig=oVx3KM2d2o%2Foqzg5SQI7sGH%2FnOQA5r%2FvX4OFRfvPp38%3D) The itemized details confirm that the cost adjustment was applied correctly to add additional budgeted costs to the project. You can see two sold estimates, which is expected because the initial $200 in costs came from the initial sold estimate and the later $2,000 in costs came from the cost adjustment. > [!NOTE] > **Note:** Because cost adjustments don't change the project total, cost adjustments won't be seen in the Deductions column in the Change Order Summary section of the Continuation Sheet. Only changes to the contract value are represented in the Change Order Summary section. ![Summary of change orders showing total additions and deductions for the month.](https://cdn.document360.io/961862ab-d0f2-4d91-bb62-a62ee8184eff/Images/Documentation/use-change-orders-to-reflect-cost-adjustments-image-su8t7kc9.png?sv=2026-02-06&spr=https&st=2026-10-31T00%3A42%3A58Z&se=2026-10-31T01%3A42%3A58Z&sr=c&sp=r&sig=oVx3KM2d2o%2Foqzg5SQI7sGH%2FnOQA5r%2FvX4OFRfvPp38%3D) ## Want to learn more? - See [Use project labels](/construction/docs/use-project-labels) - See [Create a change order](/construction/docs/create-a-change-order) - See [Complete Application for Payment and Continuation Sheet](/construction/docs/complete-application-for-payment-and-continuation-sheet) - See [Build an estimate and add estimates to opportunities](/construction/docs/add-an-estimate-to-an-opportunity) A sales tech sells an estimate. -or- A service, maintenance, or install tech sells an estimate. -or- A CSR sells an estimate over the phone. Let's say the estimate total is below the sold threshold (the customer wants to schedule the work, but hasn't fully decided). [Learn more →](https://help.servicetitan.com/docs/understanding-estimates-vocab) · [See the full glossary →](https://help.servicetitan.com/docs/glossary-overview)